Case Study: Phased Building Envelope Restoration at Calvary Academy

Peter Merlo

The Challenge


Calvary Academy, a private school in South Holland, Illinois, was experiencing progressive exterior deterioration across its masonry and concrete facades. Years of weather exposure had led to hairline cracking, control joint failures, ineffective sealants, and improperly overlapping metal copings as well as a hastily repointed brick parapet wall. During inspection, water staining was observed on the gym floor and interior walls, with active leaks affecting the boys’ and girls’ bathrooms, hallways, and the library. Damage at the bathrooms and library areas stemmed from the improper joint preparation prior to repointing of the brick parapet wall above those areas while hallways, gym wall and floor damages were due to joint sealants being past their serviceable lifespans, hairline fractures and metal copings not having the proper overlap. These issues compromised water management and raised long-term concerns about facade durability and interior performance.


With multiple elevations requiring attention and ongoing school operations to consider, Calvary’s leadership needed a phased solution that would be minimally disruptive, technically sound, and built to last.


The Solution


Our team developed and executed a two-year restoration plan that prioritized long-term performance, safety, and efficient project staging.



Phase 1 – 2024 Work


East Elevation Focus:


  • Concrete & Joint Repairs:
  • Repaired surface cracks (~1/16" wide).
  • Replaced failing control joints using Sikaflex®-15 LM, a low-modulus, high-movement joint sealant ideal for dynamic wall conditions. It also provides a paintable surface.


A RestoreWorks technician performing sealant replacement and control joint repairs from a boom lift at Calvary Academy. The image shows active restoration work near wall openings with visible swing stage setup in the background.



  • Sealant Upgrades:
  • Replaced window and door frame to masonry perimeter sealants.
  • Installed DOWSIL™ 123 Silicone Seal pre-formed strips at metal coping joints for clean, reliable expansion joint sealing, including on the gym’s south elevation. We provided the DOWSIL as a semi-permanent repair and let them know that the copings should be addressed by a roofing contractor.


  • Masonry Restoration:
  • Ground and repointed brick and CMU as marked on east elevation.
  • Installed new caulking at roof flashings transitioning between masonry and asphalt shingles.


  • Stair Tower Repairs:
  • Repointed CMU stair towers where mortar failed.
  • Replaced damaged units (up to 3 per tower) and installed retrofit weeps at entry door lintels.



Pre-restoration view of Calvary Academy showing visible surface staining, deteriorated sealant joints, and water runoff patterns on the concrete facade. Two individuals assess the building conditions near the entrance.



Phase 2 – 2025 Work


North, West, and South Elevations:


  • Repeat Base Repairs: Concrete crack repair, control joint and sealant replacement, and wall cleaning across north and west elevations using the same proven materials and approach.


  • Stair Tower Repairs (South Elevation):
  • Same scope as 2024 with localized repointing, block repair, caulking, and weep installation.


  • Painting:
  • Ascher Brothers returned to apply Modur Elastomeric coatings on all applicable surfaces. A second coat was offered as an add-alt for extended service life.


Site Access Coordination:



  • Swing stage and boom lift access for the east elevation.
  • Drive/parking lane staging for remaining elevations.
  • Lift storage planned nightly in northeast or northwest parking lots to avoid interfering with school activities.


Aerial site plan of Calvary Academy showing completed 2024 scope areas, planned 2025 repair zones, and equipment/material staging areas. The map includes directional arrows for entry paths and blocked drive paths to support safe project sequencing during school operations.



Why It Worked


  • Durable, Specification-Based Repairs: Use of DOWSIL™ 123 and Sikaflex®-15 LM provided resilient, high-performance joint and sealant systems designed to accommodate movement and prevent water intrusion.


  • Phased Strategy: Sequencing the project over two years ensured budget efficiency and allowed ongoing use of school facilities without disruption.


  • Union Execution: All masonry and painting work met union standards for safety, quality, and insurance compliance, an essential factor for schools and public-facing facilities.



  • Strategic Collaboration: RestoreWorks coordinated closely with subcontractor Ascher Brothers to deliver a smooth, high-quality finish across all coated surfaces.


The Result


The Calvary Academy restoration delivered renewed facade performance with a professional finish, improved water management, and extended material longevity. A thorough inspection by a skilled tradesman with experience in water infiltration allowed us to quickly identify the source of the leaks. Once the crack repairs and joint sealant replacements were completed, the interior leaking stopped entirely. This occurred before the elastomeric coatings and DOWSIL™ 123 strips were even applied. Our union team provided skilled execution and careful coordination from planning to close-out. This project reinforced our commitment to protecting the building envelopes of commercial properties across the greater Chicago area.


Client Feedback


Here’s what Karen Pender, Head of School at Calvary Academy, had to say about the project:

"We recently had the pleasure of working with RestoreWorks on a project that included extensive brick work, masonry repairs, CMU and stair tower repairs, along with replacement of control joints. We couldn’t be more pleased with the results.
From start to finish, the entire crew was extremely polite, hardworking, and attentive to detail. Their professionalism and respect for the property were evident every step of the way.
A special thank you goes to the job foreman, Donnie Zeiger, and Christian Kundel, the project manager, whose conscientious leadership and exceptional attention to detail truly stood out. They ensured every aspect of the project was completed with precision and care, going above and beyond to deliver outstanding quality.
I highly recommend RestoreWorks to anyone in need of expert masonry or structural repair. Their craftsmanship and commitment to excellence are top-notch."
Completed facade at Calvary Academy following base repairs, perimeter sealant replacement, and application of Modur Elastomeric Coating. The restored concrete surface appears clean and uniform beneath a partly cloudy sky.
High-rise buildings in a city, with workers on exterior scaffolding platforms performing maintenance on a beige facade.
By Peter Merlo April 1, 2026
Plan building façade restoration in Chicago for 2026. Learn how inspections, freeze–thaw cycles, and compliance impact cost, timing, and scope.
Brick wall with a window sill, featuring red-brown bricks and a vertical seam.
By Peter Merlo March 26, 2026
Spring water damage often gets blamed on cracks, failed mortar joints, or deteriorated sealants. In many cases, the real issue starts earlier, at expansion joints that were never designed, detailed, or maintained to manage seasonal movement.  For commercial and multi-family buildings in Chicago, expansion joints are a primary defense against moisture intrusion during spring thaw. When they fail, water finds its way behind masonry, into wall assemblies, and down to steel and concrete elements that were never meant to stay wet.
Split view: building before and after cleaning. The right side shows a cleaner building.
By Peter Merlo March 25, 2026
Spring masonry cleaning removes winter salt and moisture so hidden damage is exposed early, helping Chicago buildings avoid larger repairs later in the year.
Bricklayer applying mortar to brick wall with a trowel.
By Peter Merlo March 12, 2026
Learn about mortar joint repairs, why it matters for Chicago buildings, and how the approach protects overall durability and appearance.
Bricklayer applying mortar to a brick corner on a building, wearing gloves.
By Peter Merlo March 11, 2026
Learn the key signs your Chicago building needs tuckpointing before spring 2026, from failing mortar and efflorescence to leaks, spalling, and more.
Snowy balcony view, snow-covered railings, and distant buildings with snow-covered trees.
By Peter Merlo March 11, 2026
Chicago winters speed up balcony damage. Learn the warning signs, inspection steps, and repair options to prevent structural risk for multi-family buildings.
Two construction workers in safety vests and hard hats looking up at a building under construction.
By Peter Merlo March 4, 2026
Use this 2026 spring masonry inspection checklist to identify freeze–thaw damage, moisture issues, and repair priorities before small problems get worse.
Construction site covered in white tarp, surrounded by snow, with gray cinder block wall on the left.
By Peter Merlo February 25, 2026
Concrete repair in winter is possible in Chicago, but not all repairs should move forward. Learn what can be done safely and what should wait.
Brick building with metal scaffolding above windows, against a blue sky.
By Peter Merlo February 17, 2026
Use this checklist to choose a masonry restoration contractor for 2026 projects, with guidance on experience, risk, and Chicago-area building conditions.
Close-up of a window frame sealed to red brick exterior. Gray caulk seals the edges.
By Peter Merlo February 11, 2026
Failed sealant is a common cause of moisture intrusion in Chicago buildings. Learn how water enters, key warning signs, and when to call a caulking contractor.